It’s beginning to look a bit like Xmas….

It’s beginning to look a bit like Xmas….

December 14 2018
This year, we have donated £3,000 to two charities that are close to our hearts at GDL.  This year Forth One’s Mission Christmas have received £1500, which has gone...
Dr Ian Murray’s appointment boosts our Geotechnical team

Dr Ian Murray’s appointment boosts our Geotechnical team

October 25 2018
We have confirmed the expansion of our Geotechnical team with the appointment of Dr Ian Murray. On completion of a Civil Engineering Masters at Strathclyde University and a PHD...
We share our experience on new home project

We share our experience on new home project

September 26 2018
Birnam Crescent in Bearsden was an extensive enabling works contract to increase site levels and create the required development platform for 20 new homes for major UK housebuilder, CALA...
We’re making the ground move in Hamilton

We’re making the ground move in Hamilton

August 17 2018
Our team has begun work on a new 30-week contract to deliver a soil modification and bulk earthworks package that will create a development platform to facilitate new-build housing...
Our piling division goes from strength to strength with completion of rail project

Our piling division goes from strength to strength with completion of rail project

August 6 2018
With a project duration of just 16 days, we delivered an impressive 88 CFA piles with a 600mm diameter to depths of 28.5m whilst ensuring the railway remained operational....