The Broomhouse development is located on farmland in Baillieston, Glasgow.
We carried out a substantial topsoil strip to allow the cut and fill and stabilisation operations to proceed. Our GPS-guided excavators and dozers were used to achieve the required design levels for the development to allow for the construction of new two storey housing.
As part of the bulk earthworks operations, stabilisation techniques were employed to allow the re–use of site won soils to be maximised, and in turn the requirement to dispose of unsuitable excavated materials off-site and import replacement granular materials was mitigated.
We also completed the construction of the Suds Pond which will accommodate the Surface Water Drainage for the development. These works were completed by utilising site won material which was blended to meet the specification outlined by the project engineer.