Key Works
Mass Soil Mixing
Main Contractor
Balfour Beatty
Date / Duration
November 2018 / 10 wks
Enabling works contract to provide a working platform across the site for the new high school, producing stabilised piling mats for the internal areas and reducing external make-ups.
Project challenges / GDL solutions
- Working alongside existing live school and occupied housing meant that keeping disruption to a minimum was critical.
- Winter working so dark nights and freezing conditions made the process more complex.
Project benefits for the client
- By forming working platforms across the entirety of the site the follow-on civil engineering and building works were simplified and the programmes reduced.
- Reduction in export / import requirements provided financial savings as well as minimising disruption to the local community and reducing the carbon footprint of the contract.
Download as a PDF < Back