Client
Barratt Homes
Key Works
Bulk Earthworks / Crushing / Impact Compaction / Soil Modification / Remediation
Date / Duration
June 2022 / 14 weeks
Cut / Fill Volume
70,000m3

Enabling works for a new residential development.

Project challenges / GDL solutions

  • Site alongside existing residential area.
  • Former factory site with low levels of contamination within made ground.

Project benefits for the client

  • Simplified foundation construction and financial savings.
  • Minimising export / import brought, cost savings, environmental benefits and efficiency.