Key Works
Bulk Earthworks / Crushing / Impact Compaction / Soil Modification / Remediation
Date / Duration
June 2022 / 14 weeks
Cut / Fill Volume
70,000m3
Enabling works for a new residential development.
Project challenges / GDL solutions
- Site alongside existing residential area.
- Former factory site with low levels of contamination within made ground.
Project benefits for the client
- Simplified foundation construction and financial savings.
- Minimising export / import brought, cost savings, environmental benefits and efficiency.