Morgan Sindall
Key Works
Bulk Earthworks / Soil Stabilisation / Remediation
Date / Duration
January 2022 / 17 weeks
Topsoil Volume
6,708m3
Cut / Fill Volume
11,135m3

Enabling works for the new community hub bringing together Carnbroe and Sikeside primary schools and nursery class.

Project challenges / GDL solutions

  • Tight timescale / phased handover.
  • Robust Pollution Prevention Plan due to close proximity to watercourse.

Project benefits for the client

  • Reduction in export / import requirements provided financial savings as well as minimising disruption to the local community and reducing the carbon footprint of the contract