Key Works Delivered on Site
Earthworks
Soil Modification
Soil Stabilisation
Date / Duration
Ph1 - July 2019 /4 wks
Ph2 - June 2020 / 3wks
Cut/Fill Volume
Ph1 - 14,000m3
Ph2 - 10,450m3
Appointed by Bellway Homes to provide modified housing platforms to eliminate the need for piling and to treat on-site materials to provide a road capping replacement material.
Project challenges / GDL solutions
- Fill placed by another earthworks contractor to a lesser specification had to be excavated to allow for treatment and replacement to achieve a full structural specification to allow standard stiffened foundations in lieu of piled foundations.
- Working in a very tight working area alongside the follow on contractor meant that the careful programming and co-ordination of our works was crucial.
Project benefits for the client
- A reduction in the number of piled properties resulted in significant costs savings and simplified house foundation construction for the follow on groundworker.
- A stabilised capping replacement material was provided in lieu of imported stone.