Client
Bellway Homes
Key Works Delivered on Site
Earthworks
Soil Modification
Soil Stabilisation
Date / Duration
Ph1 - July 2019 /4 wks
Ph2 - June 2020 / 3wks
Cut/Fill Volume
Ph1 - 14,000m3
Ph2 - 10,450m3

Appointed by Bellway Homes to provide modified housing platforms to eliminate the need for piling and to treat on-site materials to provide a road capping replacement material.

Project challenges / GDL solutions

  • Fill placed by another earthworks contractor to a lesser specification had to be excavated to allow for treatment and replacement to achieve a full structural specification to allow standard stiffened foundations in lieu of piled foundations.
  • Working in a very tight working area alongside the follow on contractor meant that the careful programming and co-ordination of our works was crucial.

Project benefits for the client

  • A reduction in the number of piled properties resulted in significant costs savings and simplified house foundation construction for the follow on groundworker.
  • A stabilised capping replacement material was provided in lieu of imported stone.
Download as a PDF < Back
Search
Close
Thank you

Thank you for joining our mailing list. We include an unsubscribe link in every message we send so you can leave our list at any time.

Close