Client
Barratt Homes
Key Works
Bulk Earthworks / Soil Modification
Date / Duration
Feb 2022 / 26 wks
Topsoil Strip
43,610m3
Cut / Fill Volume
135,300m3

Enabling works for a new residential development.

Project challenges / GDL solutions

  • Significant amount of upfill meant that many houses would have been piled without modification of onsite soils to provide structural podiums for the houses.
  • Careful consideration had to be given to protected trees to be retained on site.

Project benefits for the client

  • Our approach removed the requirement for abnormal foundations which in turn both brought significant savings and simplified follow on works for the ground-worker.
  • Minimising export / import brought, cost savings, environmental benefits and efficiency.